Wednesday, 24 February 2010

Shooting schedule

In order for thr group to get an idea of what needed to be done, when it needed to be done and dead that must be met we arranged a shooting schedule.

Date, Time and What it is we are doing?

20th Jan Period 1+2, Finish planning story board

26th Jan Periods 3+4 ,First shots - Woods

27th Jan Periods 5+6, Filming P.O.V + Flashback shots

29th Jan Period 1+2, Uploading footage and begin editing

31st Jan All day, Finish Film

1st Feb Period 5+6, Uploading and editing

2nd Feb Period 3+4, Editing

3rd Feb Period 1+2, Editing

9th Feb Period 3+4, Final edits

-------------------------------------------------------------------

Above is a copy of the shooting schedule put together by the group, of course we tried to stick to this but by no means was it easy,and on a number of occasions it required us to use are spare time to ensure we were up to date with it.